The Ginza 6-chome Urban Redevelopment Consortium herewith notifies the press of its revised construction schedule for the Ginza 6-chome District 10 Category 1 Urban Redevelopment Project, as follows:

 

Planned Completion
Original: November 2016
Revised: End of January 2017

Reason
Construction will be delayed due to unforeseen underground obstructions that exceed original estimations.